In this week's OUR HOUSE - Construction Updates for the week ending 05/02/2026:
- Entry walls are up!
- The shop interior walls are up
- The 2nd floor mezzanine is starting to take shape as track is being laid for new rooms.
- Both locker room walls are up!
- Our new restrooms are taking shape as well as the kitchen, IT and storage rooms in the back!
- The chiller is on site and starting to be put together (no photos)
Overall A TON is happening and we are excited to see the progress!!!
Ice Grid contractors scheduled to be here last week of May!!!